As with all Big Yellow Storage Units, we were appointed by BYSS pre-tender to assist and develop the design with the architect and consulting engineer. This complex structure was constructed in two visits, the first being erected using a mobile crane sat outboard the double basement. Because the building footprint is a large proportion of the size itself, the latter visit was erected using the site tower crane with three partial handovers to allow follow-on trades to commence.